The Lodge is getting more attention now that the cabins are almost done. They have let the foundations on the 2 new sides and have started the flooring for both. The back wing that is going to be the teaching kitchen has had screening filled and packed and they are starting the concrete floors. The addition with the bathrooms has had the foundation set and the subfloors are coming along. They started scrapping shingles off today too.