The snow has been flying and the temperatures are super cold but the progress is still moving forward at at a steady pace. The ground is frozen and they are having to jack hammer 14-16 inches into the frozen ground just to get the footers set. They have started the walls on one side and the add on floors.

We are going to gradually move the electricity to underground for safety and maintenance purposes. The cabins are on lots of large rocks so doing this has proven to bit a bit of a challenge also but it coming along very well with some ingenuity.

The camp road has taken some wear and tear with all the moisture and heavy trucks so we are doing what we can to try to grade it in between freezings. We have asked H&M to help us out with gravel also.